Bỏ qua để tới nội dung chính
Đăng nhập với Microsoft
Đăng nhập hoặc tạo một tài khoản.
Xin chào,
Chọn một tài khoản khác.
Bạn có nhiều tài khoản
Chọn tài khoản bạn muốn đăng nhập.
Tiếng Anh
Chúng tôi rất tiếc. Bài viết này không có bằng ngôn ngữ của bạn.

< More Project help

This topic is for organizations that track time and task progress using separate views.    Not sure if this is for you?

Sometimes the hours you’ve spent on a task don’t match up with the percent of work you feel like you’ve completed on the task. For example, you may have completed 20 of 40 hours on a task, but you may not feel that you are 50% complete. You may think you are farther along, say 75% complete, or a bit behind, maybe 25% complete.

When you communicate your estimated percent complete, this is your task progress.

  1. Click Tasks on the Quick Launch.

    Tasks view on the Quick Launch

  2. Fill out your hours on the right side of the grid.

    Entering hours in the Tasks view

    The % Work Complete column, on the left side of the grid, will be automatically updated with the percent complete, using this math:

    Actual Work / [Actual Work + Remaining Work] = % Work Complete

    If you don’t see the task that you want to update, click Tasks > Add Row.

    Add Row

    If you’re completely done with a task, select the check box for the task, and then click Tasks > Mark Complete. Percent complete is updated to 100%.

    Mark Complete

  3. Send your updates to the project managers for your tasks.

    • If you’re ready to send all of your updates, click Tasks > Send Status > All Tasks.
      All Tasks

    • If you only want to submit some of your updates, select the check box for each task, and then click Tasks > Send Status > Selected Tasks.
      Selected Tasks

But the percentage doesn’t look accurate…what do I do?

Remember how percent complete is calculated?

20 hours completed / 40 hours scheduled = 50% complete

You know how much you worked, and you have an idea about what percentage of the total work that represents, so what you’ll need to adjust is the number of hours that are scheduled for the task.

For example, let’s say you’ve worked 20 hours, but you really only feel about 25% complete on the task. That means that you really think the task will take 80 hours, not 40, because 20 hours is 25% of 80 hours. Here’s what the math looks like:

20 hours completed / 80 hours scheduled = 25% complete

To adjust the hours scheduled, you can either change the hours in the Work column, to reflect the 80 total hours, or you can change the hours in the Remaining Work column, to reflect the additional work left to do.

In this example, you’re saying that you think the whole thing will take 80 hours, and you’ve already completed 20 of those hours. That means you have 60 hours of remaining work. When you enter 60 in the Remaining Work column, the % Work Complete column is updated to reflect the percentage that you feel is more accurate.

Read more about submitting your remaining work to the project manager.

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Thông tin này có hữu ích không?

Điều gì ảnh hưởng đến trải nghiệm của bạn?
Khi nhấn gửi, phản hồi của bạn sẽ được sử dụng để cải thiện các sản phẩm và dịch vụ của Microsoft. Người quản trị CNTT của bạn sẽ có thể thu thập dữ liệu này. Điều khoản về quyền riêng tư.

Cảm ơn phản hồi của bạn!

×