Inactivate a task

When you inactivate a task, it stays in the project plan, but does not affect resource availability, the project schedule, or how other tasks are scheduled.

This feature is only available in Project Professional.

  1. Click View, and then in the Task Views group, click Gantt Chart.

    Task Views group on the View tab.

  2. In the table, select the number of the task you want to inactivate.

  3. Click Task, and then in the Schedule group, click Inactivate.

    Inactivate button in the Schedule group of the Task tab.

    The inactive task stays in the task list, but the text is grayed out and has a line through it.

To reactivate a task, select the inactive task and then click Inactivate.

Inactivated vs. completed tasks

Inactivation is not a good way to archive completed tasks, because it could have unexpected effects on the remaining schedule.

Instead, mark the tasks as completed. Select the task and click Task. In the Schedule group, click 100%.

The Schedule group on the Task tab.

Top of Page

Phát triển kỹ năng Office của bạn
Khám phá nội dung đào tạo
Sở hữu tính năng mới đầu tiên
Tham gia Người dùng nội bộ Office

Thông tin này có hữu ích không?

Cảm ơn phản hồi của bạn!

Cảm ơn bạn đã phản hồi! Để trợ giúp tốt hơn, có lẽ chúng tôi sẽ kết nối bạn với một trong những nhân viên hỗ trợ Office của chúng tôi.

×