When you assign or remove people from a task, Project lengthens or shortens the duration of the task based on the number of resources that are assigned to it, but Project does not change the total work for the task. This is called effort-driven scheduling and is the setting Project typically uses when you assign resources to tasks.

  1. Double-click the task.

  2. In the Task Information box, click the Advanced tab.

  3. Uncheck the Effort driven check box.
    You can add the Effort Driven column to a sheet view. Right-click a column heading and then click Insert Column.

Although effort-driven scheduling works most of the time, you may want to change this to more accurately reflect what happens when resources are added or removed for a particular task. For example, you may want to see the total work increase as you add more people to a task.

Here are some exceptions to watch out for when you change the effort-driven setting.

Exception

Explanation

First assignment

Effort-driven calculations apply only after resources are initially assigned to the task. After the first resources are assigned, the work value doesn't change as new resources are assigned or removed from the same task.

Fixed work tasks

You can’t remove effort-driven scheduling from fixed-work tasks. Fixed work tasks do not have flexible work values, and are therefore always effort-driven.

Fixed unit tasks

If the assigned task type is fixed units, assigning additional resources shortens the duration of the task.

Fixed duration tasks

If the assigned task type is fixed duration, assigning additional resources decreases the individual unit values for resources.

Summary tasks

Summary tasks and inserted projects can’t be set to effort-driven.

Inserted projects

Inserted projects can’t be set to effort-driven.

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Thông tin này có hữu ích không?

Điều gì ảnh hưởng đến trải nghiệm của bạn?
Khi nhấn gửi, phản hồi của bạn sẽ được sử dụng để cải thiện các sản phẩm và dịch vụ của Microsoft. Người quản trị CNTT của bạn sẽ có thể thu thập dữ liệu này. Điều khoản về quyền riêng tư.

Cảm ơn phản hồi của bạn!

×