While you might have some general working hours in your organization, some resources may not stick to those hours. You might have one person working a night shift, or someone else working four ten-hour days. Or, you might have a piece of equipment that runs nonstop. In Project, you can set a unique schedule for a specific resource.

  1. Click Project > Properties > Change Working Time.

    Change Working Time

  2. Choose a resource from the For calendar list.

    Resources in the For calendar list

  3. Choose the right Base calendar for the resource.

    Base calendar for a resource

  4. If the working times in the calendar aren't quite right for this resource, click the Work Weeks tab, and then click Details.

    Work Weeks tab

    Note:  What about vacation? Use the Exceptions tab to add vacation to the resource's schedule. Learn more.

  5. Select the day(s) that you want to change the working times for, and then choose whether you want them to be working or nonworking time.

    Select days and working or nonworking

  6. If you chose Set day(s) to these specific working times, use the From and To columns to set the working times for the selected days.

    Set working times

  7. Click OK to return to the Change Working Time dialog box, and then click OK again.

What else can I do with calendars?

Project enables you to fine-tune scheduling using multiple calendars. If you understand how they all work together, it's easier to plan for how your project's dates will be impacted. Here are a few more articles you might find helpful in building a more accurate picture of the working and nonworking days in your organization.

PROJECTS
Set the general working days and times for a project
Create a new base calendar
Add a holiday to the project calendar

TASKS
Create a calendar for a task

RESOURCES
Add a resource's vacation time
Change resource availability without using a calendar

Tip: If you don't need a calendar anymore, delete it!

Da li vam je potrebna dodatna pomoć?

Želite još opcija?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Da li su vam ove informacije koristile?

Šta je uticalo na vaše iskustvo?
Kada kliknete na dugme Prosledi“, vaše povratne informacije će se koristiti za poboljšanje Microsoft proizvoda i usluga. Vaš IT administrator će moći da prikupi ove podatke. Izjava o privatnosti.

Hvala vam na povratnim informacijama!

×