If you want a task to end on a particular day, set a finish date for the task.

  1. Right-click a task, click Information > Advanced tab.

  2. Next to Constraint type, click Must Finish On.

  3. Next to Constraint date, fill in your end date.

Set an end date for a task

Tip:  To set the finish date back to its original setting, change the Constraint type to As Soon As Possible.

Set a deadline for a task

Keep in mind that setting the finish date can lock up your schedule in ways you don’t want. If you just need a reminder, use the Deadlinebox instead. That will create an arrow on the Gantt chart Deadline date and an indicator in the Indicator column that changes color when the deadline is passed.

  1. Right-click a task, click Information > Advanced tab.

  2. Next to Deadline,fill in your deadline date.

Set a deadline for a task

Learn other ways to control the dates in your schedule.

Top of Page

Reikia daugiau pagalbos?

Norite daugiau parinkčių?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Ar ši informacija buvo naudinga?

Kas turėjo įtakos jūsų įspūdžiams?
Paspaudus mygtuką Pateikti, jūsų atsiliepimai bus naudojami tobulinant „Microsoft“ produktus ir paslaugas. Jūsų IT administratorius galės rinkti šiuos duomenis. Privatumo patvirtinimas.

Dėkojame už jūsų atsiliepimą!

×