×
Engleski
Nažalost, ovaj članak nije dostupan na vašem jeziku.

Task Calendar GUID (task field)

Data Type    Text

Entry Type    Calculated

Description    The Task Calendar GUID field contains the generated unique identification codes for each task calendar in your project. No two task calendars will have the same Task Calendar GUID.

How Calculated    As soon as you assign a calendar to a task, automatically creates a task calendar along with its unique identifier. This identifier is stored in the Task Calendar GUID field.

Best Uses    Insert the Task Calendar GUID column into a task sheet when you need to see the unique identifier for each task calendar. This is particularly useful to help with programming and debugging custom applications.

Example    You are creating a macro that references specific resource calendars in your project. To obtain the unique identifiers for these calendars, you insert the Task Calendar GUID column into the Task Sheet.

Proširite svoje vještine korištenja sustava Office
Istražite osposobljavanje

Jesu li vam ove informacije bile korisne?

Hvala vam na povratnim informacijama!

Hvala vam na povratnim informacijama! Čini se da bi vam pomoglo kad bismo vas povezali s nekim od naših agenata podrške za Office.

×