Data Type    Date

Entry Type    Calculated

Description    The Created field contains the date and time when a task was added to the project.

How Calculated    Microsoft Project assigns the current date to this field based on the current date set in Microsoft Windows.

Best Uses    Add the Created field to a task view when you need to see when tasks were created. This can be particularly useful if you have a large number of tasks and you want to filter for tasks created within a certain time frame.

Example    You need to review all the tasks that were created after February because you want to make a global change to those tasks. Create a filter that uses the Created field to view all tasks that were created after February.

Potrebna vam je dodatna pomoć?

Želite dodatne mogućnosti?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Jesu li vam ove informacije bile korisne?

Što je utjecalo na vaše iskustvo?
Ako pritisnete Pošalji, vaše će se povratne informacije iskoristiti za poboljšanje Microsoftovih proizvoda i usluga. Vaš će IT administrator moći prikupiti te podatke. Izjava o zaštiti privatnosti.

Hvala vam na povratnim informacijama!

×