Moving tasks so that they start on a nonworking day

You have moved the selected tasks so that they start on a nonworking day. If you specify that work on tasks begins on a nonworking day, Microsoft Project cannot schedule any work to be done on those tasks during that day. The tasks will not actually start until at least the next working day. In the Gantt Chart view, nonworking time is indicated by gray vertical bars by default.

Note: Go to Set the general working days and times for a project for additional information.

Using the Planning Wizard, you can:

Move the tasks to the next working day.

Project will move the tasks so that they start on the next available working day.

Make the day a working day.

Project will move the tasks to the specified day and change that day to a working day. The working hours for this day are from 8:00 A.M. to 12:00 P.M. and 1:00 P.M. to 5:00 P.M. If your calendar uses different hours than these, you can change the hours for the new working day. On the Project tab, click Change Working Time.

If you choose to make the day a working day, be sure to check the resource calendars of any resources assigned to the tasks. If the day is not a working day for your resources, no work will be done on the tasks.

If you don't want the Planning Wizard to display this information again, select the Don't tell me about this again check box.

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×