Why can't I edit an enterprise custom field or calendar in the enterprise global template?

In Microsoft Office Project Professional 2007, you can no longer edit enterprise custom fields or enterprise calendars in the checked-out enterprise global template. Enterprise custom fields and calendars can only be edited in Microsoft Office Project Web Access, or programmatically by using the Project Server Interface (PSI) in Microsoft Office Project Server 2007.

Note: The VBA methods that were available in Microsoft Office Project Professional 2003 to modify enterprise custom fields are no longer available. Any macros that use that functionality must be rewritten to work with Office Project Professional 2007.