Watch this: Use lag and lead time

Lag and lead time enable you to be specific about the time relationships between your tasks. You can set up gaps between linked tasks, or have them overlap.

In this demo, I insert a 2-day gap between two tasks, and create an overlap between two tasks using a percent value.

Watch this Demo button

Lag and lead time

Help Button Problems watching the video? Try our troubleshooting tips.