Task Calendar GUID (task field)

Data Type    Text

Entry Type    Calculated

Description    The Task Calendar GUID field contains the generated unique identification codes for each task calendar in your project. No two task calendars will have the same Task Calendar GUID.

How Calculated    As soon as you assign a calendar to a task, Microsoft Office Project 2007 automatically creates a task calendar along with its unique identifier. This identifier is stored in the Task Calendar GUID field.

Best Uses    Insert the Task Calendar GUID column into a task sheet when you need to see the unique identifier for each task calendar. This is particularly useful to help with programming and debugging custom applications in Office Project 2007.

Example    You are creating a macro that references specific resource calendars in your project. To obtain the unique identifiers for these calendars, you insert the Task Calendar GUID column into the Task Sheet.

Applies To: Project 2010, Project Professional 2013, Project 2007, Project Standard 2013, Project Standard 2010



Was this information helpful?

Yes No

How can we improve it?

255 characters remaining

To protect your privacy, please do not include contact information in your feedback. Review our privacy policy.

Thank you for your feedback!

Support resources

Change language