Show the critical path

To meet a specific finish date for your project, it is important to carefully watch the project's critical path. You can display the critical path in any of several ways, and you can also change which tasks in your project are defined as critical tasks.

Note   By default, Project 2007 does not display a project's critical path.

What do you want to do?

Learn more about the critical path

Display the critical path for your project

Change which tasks are defined as critical

Learn more about the critical path

The critical path is a series of tasks (or sometimes only a single task) that controls the calculated start or finish date of the project. When the last task in the critical path is complete, the project is also complete.

The tasks that make up the critical path are typically interrelated by task dependencies. There are likely to be many such networks of tasks throughout your project plan.

When you display the project's critical path, Project 2007 shows only a single, overall critical path, which is the only critical path that controls the project's finish date.

However, you can set up your plan so that you can also see an additional critical path for each independent network or each series of tasks. You might find this useful for keeping track of each of the subprojects within a master project, or of each phase or milestone of a project that is divided into multiple phases.

By knowing and tracking the critical path for your project, as well as the resources that are assigned to each critical task, you can identify the tasks that can affect your project's finish date and thus discover whether your project will finish on schedule.

If it is important that your project finish on schedule, pay close attention to the tasks on the critical path, as well as to the resources assigned to those tasks. These elements all affect whether your project will finish on time.

Be aware that the critical path can change from being one series of tasks to being another series as you progress through the project's schedule. The critical path might change as critical tasks are completed, or as tasks in another series of tasks are delayed. A new critical path immediately becomes the series of tasks that you track most closely to ensure finishing on or before the desired date.

Top of Page

Display the critical path for your project

To verify that adjustments that you make to the project plan don't adversely affect the critical path, you can review the critical path and critical tasks in any of several ways.

Note   By default, Project 2007 does not display a project's critical path.

To do this

Follow these steps

Show the critical path in the context of all tasks

On the View menu, click More Views, click Detail Gantt, and then click Apply.

Show only critical tasks

On the View menu, click Gantt Chart. Then, click Critical in the Filter list Filter box on the toolbar.

To display all tasks again, click All Tasks in the Filter list on the toolbar.

You can also group all critical tasks together. On the Project menu, point to Group by and then click Critical.

Show the critical path by using the Gantt Chart Wizard

On the View menu, click Gantt Chart, and then click Gantt Chart Wizard Button image on the Formatting toolbar. Follow the instructions in the Gantt Chart Wizard to format the critical path.

By default, the Gantt chart bars and link lines for critical tasks are displayed in red. This format change overrides any direct formatting changes previously made to bar styles or to individual bars.

Note that this formatting of critical tasks applies only to the current Gantt Chart view in the current file. To use the same formatting in another file, you can use the Organizer (Tools menu) to copy formatted Gantt Charts to other files.

Show multiple critical paths in a single project

On the Tools menu, click Options, click the Calculation tab, and then select the Calculate multiple critical paths check box.

Show the overall critical path across multiple projects

Important   This procedure is only effective in a consolidated project. If you don't have a consolidated project, you must first create one.

On the Tools menu, click Options, click the Calculation tab, and then select the Inserted projects are calculated like summary tasks check box.

This is a project-level setting. All projects inserted into this project will be calculated like summary tasks.

Top of Page

Change which tasks are defined as critical

In Project 2007, a critical task has zero days of slack (float). However, you can change this default value and define a task as critical that has, for example, one or two days of slack.

  1. On the Tools menu, click Options, and then click the Calculation tab.

  2. In the Tasks are critical if slack is less than or equal to box, enter the maximum amount of slack, in days, that you want to use to define critical tasks.

  3. If you want this value to be the default value for all of your projects, click Set as Default.

To learn how to find a task's slack, see Find slack (float) in your schedule.

For instructions about changing a task's slack, see Set lead or lag time (float) between tasks.

Top of Page

Applies To: Project Standard 2007, Project 2007

Was this information helpful?

Yes No

How can we improve it?

255 characters remaining

To protect your privacy, please do not include contact information in your feedback. Review our privacy policy.

Thank you for your feedback!

Change language