Preleveled Start (task field)

Data Type    Date

Entry Type    Calculated

Description    The Preleveled Start field contains the start date of a task as it was before resource leveling was done.

How Calculated    Before Microsoft Office Project levels resources, it saves the start dates for tasks in the Preleveled Start field.

Best Uses    Add the Preleveled Start field to a task view if you want to examine the effects of resource leveling on your project's start dates.

Example    Two resources in your schedule were overloaded, so you applied resource leveling to the project. You now want to see the effects of the leveling on your task start dates. You add the Preleveled Start field next to the Start field in the Task Sheet view to make your comparisons.

Remarks    You can use the Leveling Gantt view to see the preleveled start date shown with the preleveled Gantt bars. Once you've leveled the project, specific tasks will have preleveled start dates that you cannot remove.

Applies To: Project 2010, Project Professional 2013, Project 2007, Project Standard 2013, Project Standard 2010

Was this information helpful?

Yes No

How can we improve it?

255 characters remaining

To protect your privacy, please do not include contact information in your feedback. Review our privacy policy.

Thank you for your feedback!

Change language