Preleveled Finish (task field)

Data Type    Date

Entry Type    Calculated

Description    The Preleveled Finish field contains the finish date of a task as it was before resource leveling was done.

How Calculated    Before Microsoft Office Project levels resources, it saves the current finish dates for tasks in the Preleveled Finish field.

Best Uses    Add the Preleveled Finish field to a task sheet if you want to examine the effects of resource leveling on your project's finish dates.

Example    Two resources in your schedule were overloaded, so you applied resource leveling to the project. You now want to see the effects of the leveling on your task finish dates. You add the Preleveled Finish field next to the Finish field in the Task Sheet view to make your comparisons.

Remarks    You can use the Leveling Gantt view to see the preleveled finish date shown with the preleveled Gantt bars. Once you've leveled the project, specific tasks will have preleveled finish dates that you cannot remove.

Applies To: Project 2007, Project 2010, Project 2010 Standard, Project Professional 2013, Project 2013 Standard



Was this information helpful?

Yes No

How can we improve it?

255 characters remaining

To protect your privacy, please do not include contact information in your feedback. Review our privacy policy.

Thank you for your feedback!

Support resources

Change language