NETWORKDAYS function

Returns the number of whole working days between start_date and end_date. Working days exclude weekends and any dates identified in holidays. Use NETWORKDAYS to calculate employee benefits that accrue based on the number of days worked during a specific term.

Syntax

NETWORKDAYS(start_date,end_date,holidays)

Important   Dates should be entered by using the DATE function, or as results of other formulas or functions. For example, use DATE(2008,5,23) for the 23rd day of May, 2008. Problems can occur if dates are entered as text.

Start_date     is a date that represents the start date.

End_date     is a date that represents the end date.

Holidays     is an optional range of one or more dates to exclude from the working calendar, such as state and federal holidays and floating holidays. The list can be either a range of cells that contains the dates or an array constant of the serial numbers that represent the dates.

Remarks

  • Microsoft Excel stores dates as sequential serial numbers so they can be used in calculations. By default, January 1, 1900 is serial number 1, and January 1, 2008 is serial number 39448 because it is 39,448 days after January 1, 1900. Microsoft Excel for the Macintosh uses a different date system as its default.

  • If any argument is not a valid date, NETWORKDAYS returns the #VALUE! error value.

Example

The example may be easier to understand if you copy it to a blank worksheet.

How to copy an example

  1. Create a blank workbook or worksheet.

  2. Select the example in the Help topic.

    Note   Do not select the row or column headers.

    Selecting an example from Help

    Selecting an example from Help

  3. Press CTRL+C.

  4. In the worksheet, select cell A1, and press CTRL+V.

  5. To switch between viewing the results and viewing the formulas that return the results, press CTRL+` (grave accent), or on the Formulas tab, in the Formula Auditing group, click the Show Formulas button.

1

2

3

4

5

6

A

B

Date

Description

10/01/2008

Start date of project

3/01/2009

End date of project

11/26/2008

Holiday

12/4/2008

Holiday

1/21/2009

Holiday

Formula

Description (Result)

=NETWORKDAYS(A2,A3)

Number of workdays between the start and end date above (108)

=NETWORKDAYS(A2,A3,A4)

Number of workdays between the start and end date above, excluding the first holiday (107)

=NETWORKDAYS(A2,A3,A4:A6)

Number of workdays between the start and end date above, excluding every holiday above (105)

Note   To convert the range of cells used for holidays in the last example into an array constant, select reference A4:A6 in the formula and then press F9.

Applies To: Excel 2007



Was this information helpful?

Yes No

How can we improve it?

255 characters remaining

To protect your privacy, please do not include contact information in your feedback. Review our privacy policy.

Thank you for your feedback!

Support resources

Change language