Link tasks in a project

You can link any two tasks in a project to show their relationship (also called a task dependency). Dependencies drive the project schedule — once you link the tasks, every change you make to the predecessor affects the successor, which affects the next one, and so on.

  1. Click View > Gantt Chart.

    Task Views group on the View tab.

  2. Hold down Ctrl and click the two tasks you want to link (in the Task Name column).

  3. Click Task > Link Tasks.

    Link button in the Schedule group of the Task tab

To remove a link, select the two linked tasks and then click Task > Unlink Tasks Unlink Tasks button on the Tasks tab of the ribbon..

Project creates a simple finish-to-start task link by default, which means the first task (the predecessor) needs to finish before the second task (the successor) can start.

Project supports four kinds of task links. If you want to change the link type, see Change a task link.

More ways to link tasks

Insert a task between linked tasks

Link tasks in a Network Diagram

Link tasks in a Calendar

Link manually scheduled tasks

Other ways to link tasks

Insert a task between linked tasks

With Project 2013, you can autolink tasks — insert a new task between linked tasks, and have the new task automatically link to the surrounding tasks. But to use this feature, you first need to turn it on:

  1. Click File > Options.

  2. In the Project Options dialog box, click Schedule and scroll to the Scheduling options in this project section.

  3. Select the Autolink inserted or moved tasks check box.

  4. Insert the new task.

Top of Page

Link tasks in a Network Diagram

  1. Click View > Network Diagram.

    Image of Network Diagram button on the View tab.

  2. Point to the center of the predecessor task box.

  3. Drag the line to the successor task box.

    Image of two tasks linked on a network diagram

Top of Page

Link tasks in a Calendar

  1. Click View > Calendar.

    View tab, Task Views group, Calendar button.

  2. Point to the predecessor task’s calendar bar.

  3. Drag the line to the successor task's calendar bar.

Top of Page

Link manually scheduled tasks

When you link a manually scheduled task to another task, Project places the manually scheduled task relative to the other task.

You can configure Project 2013 so that a manually scheduled task does not move when you link it to another task:

  1. Click File > Options.

  2. In the Project Options dialog box, click Schedule and scroll to the Scheduling options in this project section.

  3. Uncheck the Update manually scheduled tasks when editing links check box.

Learn more about manually and automatically scheduled tasks.

Top of Page

Other ways to link tasks

  • If you have tasks that depend on the successful completion of an entire project, consider setting up a master project.

  • To highlight how a single task relates to other tasks, use task paths.

Top of Page

Applies To: Project Professional 2013, Project 2013 Standard



Was this information helpful?

Yes No

How can we improve it?

255 characters remaining

To protect your privacy, please do not include contact information in your feedback. Review our privacy policy.

Thank you for your feedback!

Support resources

Change language