I imported a project and now my costs are not accruing correctly

Symptoms

The resource, task, and project costs data in your project is not accruing as you expected.

Cause

You may have set the accrual method as the default in an earlier version of Microsoft Office Project. When you import files in MPX format from an earlier version of Microsoft Office Project, the accrual method of any earlier version may overwrite the current version's default prorated method.

Resolution

You can manually change how costs accrue.