Created (resource field)

Data Type    Date

Entry Type    Calculated

Description    The Created field contains the date and time when a resource was added to the project.

How Calculated    Microsoft Office Project assigns the current date to this field based on the current date set in Microsoft Windows.

Best Uses    Add the Created field to a resource view when you need to see when resources were added to the project. This can be particularly useful if you have a large number of resources and you want to filter for resources added to the project within a certain time frame.

Example    You need to update the billing code for all the resources that were added to your project after June 30. Use the Created After filter to view all resources with a date in the Created field that falls after June 30.

Applies To: Project 2010, Project Standard 2007, Project 2007, Project Standard 2010

Was this information helpful?