Add a task to your timesheet

More articles about: Project Online | Project Server

Tasks assigned to you that are scheduled for the dates in the current timesheet period will be automatically included on your timesheet. Sometimes, however, you might start work on a task early, for example, and need to add a task to your timesheet that isn’t automatically included. You can add a task to your timesheet, and your time will be accounted for in the project.

  1. Click the Timesheet tab on the ribbon.

Timesheet tab

  1. Click Add Row, and then choose the kind of task you want to add.

Add Row

After adding the task, you can enter your hours for that task.

Applies To: Project Server 2013, Project Online