Sign in with Microsoft
Sign in or create an account.
Hello,
Select a different account.
You have multiple accounts
Choose the account you want to sign in with.

Making changes in the timephased portion of the view causes a conflict with another task

The timephased edit will cause one task to finish after the start of the task to which it is linked.

Using the Planning Wizard, you can:

Keep the timephased edit and ignore the link.

Microsoft Project will keep the edits you made to the timephased portion of the view and ignore the link between the tasks. It will do this by putting a constraint on the task that you're editing.

Ignore the timephased edit.

Project will remove the timephased edits you made and will not change the links or constraints that are applied to the tasks.

If you don't want the Planning Wizard to display this information again, select the Don't tell me about this again check box.

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×