Rescheduling uncompleted work on unstarted tasks with constraints

Microsoft Project can't reschedule work on unstarted tasks with moderate or inflexible constraints. Finish No Later Than (FNLT), Start No Later Than (SNLT), Finish No Earlier Than (FNET), and Start No Earlier Than (SNET) are moderate constraints. Must Start On (MSO) and Must Finish On (MFO) are inflexible constraints.

Project will reschedule work on unstarted tasks with flexible constraints. As Soon As Possible (ASAP) and As Late As Possible (ALAP) are flexible constraints.

If you want to reschedule the work on these tasks, set the constraints to As Soon As Possible (ASAP) and try to reschedule these tasks again.

If you don't want the Planning Wizard to display this information again, select the Don't tell me about this again check box.

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×