Sign in with Microsoft
Sign in or create an account.
Hello,
Select a different account.
You have multiple accounts
Choose the account you want to sign in with.

Making changes in the timephased portion of the view causes a conflict with another task

The timephased edit will cause one task to start before its predecessor task. Because tasks in this project are not required to honor their constraint dates, the only way to keep the timephased edit on the task is to remove one or more of its task links.

Using the Planning Wizard, you can:

Keep the timephased edit and remove the link.

Microsoft Project will keep the changes you made to the timephased portion of the view and remove the link between the tasks. To have Project not override the constraints you place on tasks when there is a scheduling conflict, click the File tab, click Options, then in the Schedule tab check the Tasks will always honor their constraint dates checkbox.

Do not remove the link.

Project will remove the timephased edit you made and will not change the links or constraints that are applied to the tasks.

If you don't want the Planning Wizard to display this information again, select the Don't tell me about this again check box.

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×