Sign in with Microsoft
Sign in or create an account.
Hello,
Select a different account.
You have multiple accounts
Choose the account you want to sign in with.

After entering any of the various rate-based resource costs, cost resources, and fixed costs, you’re ready to check if the overall project cost is within budget, but it’s not very clear where to find that cost total, or perhaps you have overtime costs that you need to calculate.

That’s because cost totals for the project, tasks, resources, and assignments are available in different views, and for some cost totals you open the Cost table to see them.

Let’s start with showing the total cost for the entire project:

  1. Choose Project > Project Information.

    Project Information on the Project tab
  2. In the Project Information dialog box, choose Statistics.

  3. In the Project Statistics dialog box, review the cost totals for the project in the Cost column.

Tip: You can also see this cost total on the project summary task in the Gantt Chart view. If it’s not shown, select the Project Summary Task box on the Format tab.

Project Summary Task on the Format tab

View cost totals for tasks

  1. On the View tab, choose the arrow for Gantt Chart, and then choose More Views.

    Gantt Chart menu
  2. In the Views list, pick Task Sheet, and choose Apply.

  3. Choose View > Tables, Cost to apply the Cost table.

    Cost table in the Tables menu
  4. In the Total Cost field, review the cost total for tasks.

    Press Tab to move to this field if you don’t see it.

Note: If your tasks total costs appear to be incorrect, see the troubleshooting steps below.

View total costs for resources

  1. Choose View > Resource Sheet.

    Resource Sheet on the View tab
  2. Choose View > Tables, Cost to apply the Cost table.

    Cost table in the Tables menu
  3. Review the cost columns.

View total costs for assignments

  1. Choose View > Task Usage.

    Task Usage button on the View menu

    This view shows tasks with the resources that are assigned to them.

  2. Choose View > Tables, Cost to apply the Cost table.

    Cost table in the Tables menu
  3. Review the costs columns.

    The cost of each task reflects the resources assigned to it.

If your task's total costs appear to be incorrect

The expected amount of a task's total cost may seem to differ from the calculated sum of its rate-based costs, per-use costs, and fixed costs. Total costs are the sum of rate-based costs, per-use costs, and fixed costs. Note that costs are calculated only after resources are assigned to tasks.To resolve discrepancies, try the following:

  • Check the assignment total costs and the task's total costs by using the Task Usage view with the Cost table applied. Look for any per-use costs or fixed costs that may have been overlooked.

  • Verify total costs at the task-level. Fixed costs do not roll up to the Fixed Cost field at the summary task-level.

  • Verify that all resources with cost information are assigned to tasks.

  • Verify that you have applied the correct cost rate table to the resource assignment.

Calculate overtime costs

By default, Project calculates the work required to complete a task by using the standard rate of each assigned resource. Project does not calculate the cost of additional work hours by using the overtime rates that you entered until you specify those hours as overtime work. For example, if a resource is scheduled to work eight hours a day and he or she enters ten hours of actual work, the two hours of additional time isn't automatically considered overtime work.

  1. Choose View > Task Usage.

  2. Choose View > Tables > Work.

  3. Right-click the Work field and choose Insert Column.

    (In Project 2007, select the Work field, and then chose Column on the Insert menu.)

  4. In the Field name list, choose Overtime Work.

  5. In the Overtime Work field, select the resource assignment for which you want to enter overtime work.

    Press TAB to move to the field if it is not visible.

    If resource assignments are hidden, click the task's outline symbol Plus symbolto display them.

  6. In the Overtime Work field, enter the amount of overtime work for the resource assignment.

    Note: The amount of overtime work that you specify is not added to the amount of work for the task because work always represents the total amount of work. Overtime work merely represents the portion of the total amount of work that should be considered and rated as overtime. When you enter overtime work, the duration of the task may be shortened, unless the task is a fixed-duration task type.

More about costs

Enter costs for resources

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×