If you keep a list of tasks in Outlook, you can easily import all or some of its tasks into Microsoft Office Project.

  1. In Project, on the Task tab, in the Insert group, choose Task > Import Outlook Tasks

  2. In the Import Outlook Tasks dialog box, select the tasks that you want to import.

  3. Choose OK to import the tasks into the current project.

  4. In Project, schedule the tasks as needed.

    Notes: 

    • Tasks are appended to any existing tasks in the current project. If the project does not contain tasks, a new task list is created.

    • Only the task name, notes, and duration are imported. Task dates are not imported.

    • When you import tasks from Outlook, no connection is maintained between Outlook and Project. The tasks are simply copied to your project.

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×