The following are the resource fields in Microsoft Office Project. For more information, click a field name.

Accrue At (resource field)

Actual Cost fields

Actual Finish fields

Actual Overtime Cost fields

Actual Overtime Work fields

Actual Start fields

Actual Work fields

ACWP fields

Assignment fields

Assignment Delay fields

Assignment Units fields

Available From (resource field)

Available To (resource field)

Base Calendar (resource field)

Baseline Cost fields

Baseline Finish fields

Baseline Start fields

Baseline Work fields

Baseline1-10 Cost fields

BCWP fields

BCWS fields

Can Level (resource field)

Code (resource field)

Confirmed fields

Cost fields

Cost Per Use (resource field)

Cost Rate Table fields

Cost Variance fields

Cost1-10 fields

CV fields

Date1-10 fields

Duration1-10 fields

E-mail Address (resource field)

Enterprise Base Calendar (resource field)

Enterprise Cost1-10 fields

Enterprise Date1-30 fields

Enterprise Duration1-10 fields

Enterprise Flag1-20 fields

Enterprise Number1-40 fields

Enterprise Required Values (resource field)

Enterprise Required Values (resource field)

Enterprise Resource Outline Code1-29 fields

Enterprise Team Member (resource field)

Enterprise Text1-40 fields

Enterprise Unique ID (resource field)

Finish1-10 fields

Finish (resource field)

Flag1-20 fields

Generic (resource field)

Group (resource field)

Group By Summary fields

Hyperlink fields

Hyperlink Address fields

Hyperlink Href fields

Hyperlink SubAddress fields

ID fields

Inactive (resource field)

Indicators fields

Initials (resource field)

Leveling Delay fields

Linked Fields fields

Material Label (resource field)

Max Units (resource field)

Name fields

Notes fields

Number1-20 fields

Objects fields

Outline Code1-10 fields

Overallocated fields

Overtime Cost fields

Overtime Rate (resource field)

Overtime Work fields

Peak fields

Percent (%) Work Complete fields

Phonetics (resource field)

Project fields

RBS fields

Regular Work fields

Remaining Cost fields

Remaining Overtime Cost fields

Remaining Overtime Work fields

Remaining Work fields

Response Pending fields

Standard Rate (resource field)

Start fields

Start1-10 fields

SV fields

Task Summary Name fields

TeamStatus Pending fields

Text1-30 fields

Type fields

Unique ID fields

Update Needed fields

VAC fields

Windows User Account (resource field)

Work fields

Workgroup (resource field)

Work Contour fields

Work Variance fields

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×