Prijavite se pomoću Microsofta
Prijavi se ili izradi račun.
Zdravo,
Odaberite drugi račun.
Imate više računa
Odaberite račun putem kojeg se želite prijaviti.
engleski
Nažalost, ovaj članak nije dostupan na vašem jeziku.

The Remaining Cumulative Work fields contain the remaining amount of time scheduled for all resources assigned to task, accumulated over time.

There are three categories of Remaining Cumulative Work fields.

Data Type    Duration

Remaining Cumulative Work (task-timephased field).

Entry Type    Calculated

How Calculated    The Work field contains the total amount of time scheduled for a task. The Cumulative Work field contains the amount of time scheduled for resources assigned to tasks, accumulated over time. Project calculates remaining cumulative work as follows:

Remaining Cumulative Work = Total Work – Cumulative Work

Best Uses    Add the Remaining Cumulative Work field to the timephased portion of the Task Usage view to review remaining cumulative work information for tasks. You can use this information to review how much scheduled work remains to be completed for a task on a given day.

Example    The “Research” task will take 8 hours of work over three days. The scheduled work for the 3 days is 2, 5, and 1. The value in the Remaining Cumulative Work field before day 1 is 8 hours. At day 1, the remaining cumulative work is 6 hours. At day 2, it is 1 hour. At day 3, it is 0 hours..

Remaining Cumulative Work (resource-timephased field)

Entry Type    Calculated

How Calculated    The Work field contains the total amount of time scheduled for a task. The Cumulative Work field contains the amount of time scheduled for resources assigned to tasks, accumulated over time. Project calculates remaining cumulative work as follows:

Remaining Cumulative Work = Total Work – Cumulative Work

Best Uses    Add the Remaining Cumulative Work field to the timephased portion of the Resource Usage view to review remaining cumulative work information for a resource. This allows you to see how much total scheduled work remains to be completed for a resource at a given point in time.

Example    Shawn is assigned to three tasks over three days: “Research,” “Develop,” and “Test.” The total work scheduled for all tasks is 24 hours over 3 days. The scheduled work for the “Research” task over three days is 2, 5, and 1. The scheduled work for the “Develop” task over three days is 3, 5, and 2. The scheduled work for the “Test” task is 1, 1, and 4.

The Remaining Cumulative Work field for Sean before day 1 is 24 hours. The Remaining Cumulative Work field at day 1 is 18 hours. At day 2 it is 7 hours. At day 3, it is 0 hours.

Remaining Cumulative Work (assignment-timephased field)

Entry Type    Calculated

How Calculated    The Work field contains the total amount of time scheduled to complete a task. The Cumulative Work field contains the amount of time scheduled for resources assigned to tasks, accumulated over time. Project calculates remaining cumulative work as follows:

Remaining Cumulative Work = Total Work – Cumulative Work

Best Uses    Add the Remaining Cumulative Work field to the timephased portion of the Task Usage view to review information on Remaining Cumulative Work for assignments on specific tasks over a period of time. Add this field to the timephased portion of the Resource Usage view to review information on remaining work over a period of time for assignments to specific resources.

Example    Jane is assigned to 8 hours of work for the "Research" task with a duration of 3 days. The scheduled work for the 3 days is 2, 5, and 1 hours. You add the Remaining Cumulative Work field to the timephased portion of the Task Usage view. The Remaining Cumulative Work field before day 1 is 8 hours. At day 1 it is 6 hours. At day 2, it is 1 hour. And at day 3 it is 0 hours.

Top of Page

Potrebna vam je dodatna pomoć?

Želite dodatne mogućnosti?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Jesu li vam ove informacije bile korisne?

Što je utjecalo na vaše iskustvo?
Ako pritisnete Pošalji, vaše će se povratne informacije iskoristiti za poboljšanje Microsoftovih proizvoda i usluga. Vaš će IT administrator moći prikupiti te podatke. Izjava o zaštiti privatnosti.

Hvala vam na povratnim informacijama!

×