Prijavite se pomoću Microsoft naloga
Prijavite se ili kreirajte nalog.
Zdravo,
Izaberite drugi nalog.
Imate više naloga
Odaberite nalog pomoću kojeg želite da se prijavite.
engleski
Žao nam je. Ovaj članak nije dostupan na vašem jeziku.

Data Type    Date

Entry Type    Calculated

Description    The Preleveled Start field contains the start date of a task as it was before resource leveling was done.

How Calculated    Before Microsoft Office Project levels resources, it saves the start dates for tasks in the Preleveled Start field.

Best Uses    Add the Preleveled Start field to a task view if you want to examine the effects of resource leveling on your project's start dates.

Example    Two resources in your schedule were overloaded, so you applied resource leveling to the project. You now want to see the effects of the leveling on your task start dates. You add the Preleveled Start field next to the Start field in the Task Sheet view to make your comparisons.

Remarks    You can use the Leveling Gantt view to see the preleveled start date shown with the preleveled Gantt bars. Once you've leveled the project, specific tasks will have preleveled start dates that you cannot remove.

Da li vam je potrebna dodatna pomoć?

Želite još opcija?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Da li su vam ove informacije koristile?

Šta je uticalo na vaše iskustvo?
Kada kliknete na dugme Prosledi“, vaše povratne informacije će se koristiti za poboljšanje Microsoft proizvoda i usluga. Vaš IT administrator će moći da prikupi ove podatke. Izjava o privatnosti.

Hvala vam na povratnim informacijama!

×