Masuk dengan Microsoft
Masuk atau buat akun.
Halo,
Pilih akun lain.
Anda memiliki beberapa akun
Pilih akun yang ingin Anda gunakan untuk masuk.
Bahasa Inggris
Maaf. Artikel ini tidak tersedia dalam bahasa Anda.

When you inactivate a task, it stays in the project plan, but does not affect resource availability, the project schedule, or how other tasks are scheduled.

This feature is only available in Project Professional.

  1. Click View, and then in the Task Views group, click Gantt Chart.

    Task Views group on the View tab.

  2. In the table, select the number of the task you want to inactivate.

  3. Click Task, and then in the Schedule group, click Inactivate.

    Inactivate button in the Schedule group of the Task tab.

    The inactive task stays in the task list, but the text is grayed out and has a line through it.

To reactivate a task, select the inactive task and then click Inactivate.

Inactivated vs. completed tasks

Inactivation is not a good way to archive completed tasks, because it could have unexpected effects on the remaining schedule.

Instead, mark the tasks as completed. Select the task and click Task. In the Schedule group, click 100%.

The Schedule group on the Task tab.

Top of Page

Perlu bantuan lainnya?

Ingin opsi lainnya?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Apakah informasi ini berguna?

Apa yang memengaruhi pengalaman Anda?
Dengan menekan kirim, umpan balik Anda akan digunakan untuk meningkatkan produk dan layanan Microsoft. Admin TI Anda akan dapat mengumpulkan data ini. Pernyataan Privasi.

Terima kasih atas umpan balik Anda!

×