When you inactivate a task, it stays in the project plan, but does not affect resource availability, the project schedule, or how other tasks are scheduled.

This feature is only available in Project Professional.

  1. Click View, and then in the Task Views group, click Gantt Chart.

    Task Views group on the View tab.

  2. In the table, select the number of the task you want to inactivate.

  3. Click Task, and then in the Schedule group, click Inactivate.

    Inactivate button in the Schedule group of the Task tab.

    The inactive task stays in the task list, but the text is grayed out and has a line through it.

To reactivate a task, select the inactive task and then click Inactivate.

Inactivated vs. completed tasks

Inactivation is not a good way to archive completed tasks, because it could have unexpected effects on the remaining schedule.

Instead, mark the tasks as completed. Select the task and click Task. In the Schedule group, click 100%.

The Schedule group on the Task tab.

Top of Page

Da li vam je potrebna dodatna pomoć?

Želite još opcija?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Da li su vam ove informacije koristile?

Šta je uticalo na vaše iskustvo?
Kada kliknete na dugme Prosledi“, vaše povratne informacije će se koristiti za poboljšanje Microsoft proizvoda i usluga. Vaš IT administrator će moći da prikupi ove podatke. Izjava o privatnosti.

Hvala vam na povratnim informacijama!

×