Enter hours on your timesheet in Project Online

The time you spend on tasks and other non-project work is captured on your timesheet.

  1. On the Quick Launch, click Timesheet.

    Timesheet on the Quick Launch

  2. Find the task that you worked on in the list on the left side, and then follow the row across to the right side of the view.

    Main Display Area

  3. Fill in your hours across the top row of the grid, next to Actual.

    Timesheet row

    The bottom row of the grid shows the Planned hours, from when the task was initially scheduled in the project.

    Tip:  Slide the splitter in the middle over to see more of either side of the view.

    Splitter between two sides of a timesheet

Perlu bantuan lainnya?

Ingin opsi lainnya?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Apakah informasi ini berguna?

Apa yang memengaruhi pengalaman Anda?
Dengan menekan kirim, umpan balik Anda akan digunakan untuk meningkatkan produk dan layanan Microsoft. Admin TI Anda akan dapat mengumpulkan data ini. Pernyataan Privasi.

Terima kasih atas umpan balik Anda!

×