The Date1 through Date10 fields are custom fields that store any task, resource, or assignment date information you want.

There are several categories of Date1-10 fields.

Data Type    Date

Date1-10 (task fields)

Entry Type    Calculated or entered

Best Uses    Add one or more custom date fields to a task view to maintain additional date information on your tasks.

Example    You want to include an estimated completion date for the work on a milestone phase. You can add the Date1 field to a task sheet and rename it "Estimated Completion Date." Then for all milestone tasks, you enter the estimated completion date in this field.

Remarks    Any date you enter in a custom date field does not affect Microsoft Project calculations. If no date is entered, the field contains "NA."

You can create custom value lists, formulas, and graphical indicators for any of the custom date fields. You can also create custom attributes or rename the custom date field, in the Custom Fields dialog box. Specifying a formula causes the field to become read-only.

You can copy the custom fields you create, along with all their attributes, to other project files, in the Organizer dialog box.

Date1-10 (resource fields)

Entry Type    Calculated or entered

Best Uses    Add one or more custom date fields to a resource sheet to maintain additional date information on your resources. Examples include hire date, birthday, or start date on the project.

Example    You want to add birthdays to your resource information. You add the Date1 field to the Resource Sheet view, and rename it "Birthday." Then you enter the birthdays for all resources in this field.

Remarks    Any date you enter in a custom Date1 through Date10 field does not affect Project calculations. If no date is entered, the field contains "NA."

You can create custom value lists, formulas, and graphical indicators for any of the custom date fields. You can also create custom attributes or rename the custom date field, in the Custom Fields dialog box. Specifying a formula causes the field to become read-only.

You can copy the custom fields you create, along with their custom attributes, to other project files, in the Organizer dialog box.

Date1-10 (assignment fields)

Entry Type    Entered

Best Uses    Add one or more custom date fields to the sheet portion of the Task Usage or Resource Usage view to maintain additional assignment date information.

Example    You've already added the Start and Finish fields to your table. However, you want to include an estimated 50 percent completion date for the assignments on critical tasks. You add the Date1 field to the table and name it "Halfway Point." For all critical assignments, you enter the estimated 50 percent completion date in this field.

Remarks    Any date you enter in a custom Date1 through Date10 field does not affect Project calculations. If no date is entered, the field contains "NA."

Da li vam je potrebna dodatna pomoć?

Želite još opcija?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Da li su vam ove informacije koristile?

Šta je uticalo na vaše iskustvo?
Kada kliknete na dugme Prosledi“, vaše povratne informacije će se koristiti za poboljšanje Microsoft proizvoda i usluga. Vaš IT administrator će moći da prikupi ove podatke. Izjava o privatnosti.

Hvala vam na povratnim informacijama!

×