Data Type    Date

Entry Type    Calculated

Description    The Available From field shows the starting date that a resource is available for work at the units specified for the current time period.

Best Uses    Use the Available From field when you have a resource whose unit availability varies throughout the life of the project. The date shown in the Available From field indicates the beginning of the date range for the current period. Add the Max Units field to show the resource's unit availability during the current time period. Add the Available To field to show when the resource ends the period at this level of unit availability. Add the Available From field to a resource sheet when you want to view or filter dates in the Available From field for your resources.

Example    A new resource is starting work on this project about a month from now, on June 1. The resource will start the project working half-time, and then on September 1, she will go to 75 percent unit availability. On January 1, the resource will be 100 percent on the project. Use the General tab in the Resource Information dialog box to set the availability dates and their corresponding units. Then add the Available From, Available To, and Max Units fields to the Resource Sheet view so you can always see this resource's availability for the current time period.

Remarks    You cannot directly edit the Available From field. Instead, you can set up availability dates and units on the General tab of the Resource Information dialog box. The date set for the current period is shown in the Available From field.

Because Microsoft Office Project does not use the Available From date when calculating a task or project schedule, a resource can be scheduled for work beyond the availability dates. However, in this case, Project indicates that the resource is overallocated. Project also uses the Available From and Available To dates when leveling resources.

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Thông tin này có hữu ích không?

Điều gì ảnh hưởng đến trải nghiệm của bạn?
Khi nhấn gửi, phản hồi của bạn sẽ được sử dụng để cải thiện các sản phẩm và dịch vụ của Microsoft. Người quản trị CNTT của bạn sẽ có thể thu thập dữ liệu này. Điều khoản về quyền riêng tư.

Cảm ơn phản hồi của bạn!

×